Skip to content

Resources · Guide

G100 compliance for EV charging, explained

G100 import limitation lets an EV charging site draw more power than its raw connection would otherwise allow - safely, and often without a costly grid upgrade. This is what the recommendation asks for and how a charger has to behave to satisfy it.

What it is

An ENA recommendation for limiting what a site draws

G100 is an Engineering Recommendation from the UK Energy Networks Association (ENA). It sets out how large loads and microgeneration - solar PV, home and site batteries, and EV chargers - can be actively limited so they never draw more from, or export more to, the grid than the network can safely accommodate.

For EV charging the important half is import limitation: a control scheme that holds the power a site imports within an agreed capacity, adjusting charging in real time to stay inside it. Under G100 Issue 2 both import and export limitation are covered, built around Customer Limitation Schemes agreed with the Distribution Network Operator (DNO).

Why it matters

A site's raw connection is often smaller than the peak an EV charging installation would draw. Without limitation the DNO may demand an expensive, slow grid reinforcement before granting a connection. A G100 import-limitation scheme lets you commission more charging on the existing supply - the site simply promises, and provably enforces, that it will not exceed its agreed import capacity.

Who this is for

CTOs, manufacturers and operators

This reference is written for CTOs and technical decision-makers, charge point manufacturers designing G100-ready hardware, and charge point operators (CPOs) who have to keep live sites compliant as they scale.

How import limitation works

One measurement point, one control scheme, four operating states

Every G100 import-limitation scheme has the same skeleton: a place where demand is measured, a controller that decides how much charging the site can afford right now, and a small set of load states the scheme moves between as demand rises and falls.

The measurement point

Where the site's demand is read

Limitation is enforced against a measurement taken at the site boundary, where total import is visible - not at an individual charger. The scheme continuously reads that point so charging is throttled against real, whole-site demand, including everything else drawing power behind the same connection.

The control scheme

How charging is held within the limit

A controller compares measured import against the agreed capacity and modulates charge current to keep the site inside it. One or many chargers can run under a single Customer Limitation Scheme, sharing the available headroom rather than each assuming it has the whole connection to itself.

The operating states, and the transitions between them

CLS

Continuous Load State

Normal running. Site import sits at or below the agreed continuous capacity and charging is delivered at the fastest rate the remaining headroom allows. The scheme monitors the measurement point continuously so it can react before the limit is reached.

ELS

Extended Load State

A short, bounded excursion above the continuous limit is tolerated only for a defined window before the scheme must act. It is a transitional state, not a licence to run above capacity - the controller has to detect the excursion and begin reducing import promptly.

MEL

Maximum Export Limit

The absolute ceiling set by the Distribution Network Operator, the hard boundary the installation must never cross. As the load approaches it the control scheme curtails charging back into the continuous state, and for bidirectional (V2G) sites it also caps how much power can flow back to the grid.

Fail-safe

Fail-safe lockout

The failure mode. If the scheme cannot measure the site, cannot control the load, or an excursion is not corrected within the permitted window, it must fail safe and stop charging rather than keep drawing power it can no longer prove is within limits. Losing the measurement signal has to be treated as an excursion, not as an all-clear.

The scheme lives in the Continuous Load State almost all of the time. A surge in site demand can push it briefly into the Extended Load State, from which it must detect the excursion and reduce import back into continuous running before the Maximum Export Limit is threatened. The transitions matter as much as the states: a compliant charger is defined by how quickly and reliably it moves back down, not just by the limits themselves.

What it means for a charger

Designing hardware that satisfies G100

Meeting G100 is less about a single feature and more about how the charger behaves under load and under fault. Four requirements shape the design.

Dynamic load management

Charge current is adjusted in real time against a live measurement of site demand, so EV charging soaks up spare capacity without ever pushing the connection past its agreed limit. Multiple chargers coordinate as one scheme rather than competing for headroom.

Fail-safe to a safe default

If the measurement feed, a meter or a communications link fails, the charger must fall back to a conservative default rather than assume full capacity is available. Fault detection on the measurement devices is part of staying compliant, not an optional extra.

Fast, bounded response

The scheme has to detect an excursion and pull import back to the agreed capacity within a short, defined window - on the order of seconds, not minutes. Sizing the control loop and the actuation path to hit that response time is a core design constraint.

Protected, sealed settings

Limit settings are protected against unauthorised change through passwords, PINs or physically sealable access, and the equipment is type-tested to G100 so the DNO can trust the scheme without re-verifying every installation.

Get in touch

Ready to talk through your project?

Tell us what you're building and our engineers will help you scope the fastest, lowest-risk route to market. A conversation directly with the people who design the charging modules.

Your enquiry is sent directly to the Versinetic engineering team. We do not share your information with third parties. By submitting this form you agree to our Privacy Policy.